Anthropic’s rapid AI expansion is set to rely overwhelmingly on fossil fuels, with 87% of its US power coming from gas and 11% from coal by 2028. This energy mix, revealed in a November 2026 report by the Better Data Center Project, highlights a growing tension between AI scalability and environmental responsibility—particularly as the company scales compute without direct US renewable energy commitments.
The findings are based on 9.6 GW of identified data centre capacity contracted by Anthropic across the US, enough to power nearly 7 million homes. While the company claims to be exploring geothermal, wind, and solar, its only disclosed renewable investments remain in Norway and Canada. In contrast, it has committed $3.4 billion to procure 1.7 GW of on-site gas generators.
Heavy reliance on gas and coal
Anthropic’s US data centres are being built in regions where the grid relies heavily on fossil fuels. The report estimates that 25% of its power—around 2.5 GW—will come from on-site gas generators, mostly inefficient simple cycle turbines. The rest will be supplied by the grid, where new demand is met by marginal fossil plants, primarily gas and coal. Without new renewable capacity tied to these loads, the grid cannot offset the emissions.
This results in an estimated carbon intensity of 1,033–1,076 lb CO2e/MWh—35% above the US grid average. For context, the US data centre sector emitted 105 million metric tons of CO2e in 2024; Anthropic alone could add 16–36% to that figure by 2028.
Emissions comparable to major tech firms
In a mid-case scenario, Anthropic’s power use could emit 32 million metric tons of CO2e annually by 2028. That exceeds California’s entire in-state power generation emissions (31.1 million in 2024) and would surpass the combined Scope 2 emissions of Meta, Microsoft, and Google in 2025—before offsets.
These emissions stem not only from grid power but also from behind-the-meter gas plants. At facilities like Nscale’s Monarch Campus in West Virginia, Anthropic is using reciprocating engines known for high formaldehyde and hazardous air pollutant (HAP) emissions. Even SpaceX’s Colossus 2 site, which supplies up to 600 MW, relies on temporary turbines lacking selective catalytic reduction (SCR) systems, despite Anthropic’s stated air quality standards.
Health and regulatory risks
Beyond carbon, the report estimates annual health damages of $2–3 billion due to air pollution, with over 13,000 tons of nitrogen oxides (NOx) and 2,000 tons of fine particulate matter (PM2.5) released. These pollutants are linked to respiratory and cardiovascular diseases, particularly in nearby communities.
Anthropic says it requires emissions controls and follows permitting processes. However, its use of unpermitted, high-emission turbines at Colossus 2—documented as of May 2026—raises questions about enforcement and accountability in fast-tracked AI infrastructure.
What it means
For UK, UAE, US, and Kazakh tech leaders, Anthropic’s path underscores a critical trade-off: speed and energy control versus sustainability and long-term cost. Relying on gas offers immediate scalability and reduces grid dependency, but locks in high-carbon infrastructure for decades. It also increases exposure to future carbon pricing and reputational risk, especially as ESG scrutiny grows.
Unlike Google or Microsoft, which have invested heavily in renewable procurement and grid decoupling, Anthropic’s model prioritises power security over green credentials. This may appeal in energy-constrained markets like Kazakhstan or the UAE, but could hinder partnerships with climate-conscious firms in the UK or EU.
Businesses should assess not just compute availability, but energy provenance. Contracts tied to fossil-heavy grids or on-site gas may offer lower latency and pricing today, but could face regulatory headwinds tomorrow.
The data suggests that without binding renewable commitments, even cutting-edge AI firms contribute significantly to emissions growth. As AI demand drives 50–75% of global data centre energy growth, the sector’s environmental footprint can no longer be treated as a footnote.